Order Progress Tracking Report

Report IDOSM-DEMO-OPT-003 · Update #3 of 5
ClientMaple & Pine Retail Inc. (fictional), Canada
Supplier“Demo Yuxin Ceramics Co., Ltd.” (fictional)
OrderPO-DEMO-0427 · Stoneware mugs, 12,000 pcs, 3 colors · Deposit 30% paid by client
Agreed ship-ready date2026-11-20 (per PO)
Follow-up planWeekly calls in Chinese; dated evidence requested at each milestone; exceptions reported within 24 hours
Reporting period2026-10-19 to 2026-10-25 (UTC+8)
Prepared / reviewed by[Coordinator — demo] / [Reviewer — demo]

Status this week

At risk — 6 to 8 days late. Glaze for the “sage green” color (4,000 pcs) failed the supplier’s own color check and is being redone. The supplier now states a ship-ready date of 2026-11-27, 7 days after the PO date. Client decision needed: accept the new date, or ship the other two colors first (see R-02).

Milestones

#MilestonePlannedReportedEvidenceStatus
M1Materials ready (clay, glaze, cartons)10-0510-06 doneP-01, P-02Supplier Stated
M2Production start10-0810-08 doneP-03Supplier Stated
M350% formed & first firing10-2210-23 doneP-05, P-06, VC-01Observed remotely
M4Glazing & second firing11-05Delayed (sage green)P-07Supplier Stated
M5Packing complete11-18Forecast 11-25—Not Verified
M6Ready to ship11-20Forecast 11-27—Not Verified

Status key: Independently Verified we checked it ourselves against an independent source or by direct observation · Supplier Stated told or shown to us by the supplier, not independently confirmed · Not Verified could not be confirmed · Observed remotely seen by live video, not in person.

Osmanth China Business Services · SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY — not a client case. All names, numbers and addresses are invented.Page 1 of 5
SAMPLE TEMPLATE
FOR DEMONSTRATION ONLY
OSMANTHOSM-DEMO-OPT-003SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY

Progress log this period

Date (UTC+8)ContactWhat happenedEvidence
10-20 10:00Call with Mr. Chen (production)Supplier reports forming 40% complete. Photos requested.P-04
10-23 14:30Live video call, 10 minWe saw racks of fired, unglazed mugs and the kiln area by video. Counted 22 racks; supplier states ~260 pcs per rack.VC-01, P-05, P-06
10-24 09:15WeChat message from Mr. ChenSupplier reports sage green test batch “too dark”; glaze to be re-mixed. Photo of test tiles sent.P-07
10-24 11:00Escalated to clientException R-02 sent to client by email within 2 hours.—
10-25 16:00Call with Mr. ChenSupplier gives new ship-ready forecast of 11-27 and offers to ship 8,000 pcs (2 colors) on 11-20.SCF-03

Evidence index

RefTypeSourceDateStatus
P-01 – P-04PhotosSent by supplier via WeChat10-06 – 10-20Supplier Stated
P-05, P-06Screenshots from live videoTaken by OSMANTH during VC-0110-23Observed remotely
VC-01Video call noteOSMANTH10-23Observed remotely
P-07Photo of glaze test tilesSent by supplier10-24Supplier Stated
SCF-03Supplier Confirmation FormSigned by supplier10-25Supplier Stated

Supplier photos are not independent proof. Progress is “Independently Verified” only when we observe it in person.

Osmanth China Business Services · SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY — not a client case. All names, numbers and addresses are invented.Page 2 of 5
SAMPLE TEMPLATE
FOR DEMONSTRATION ONLY
OSMANTHOSM-DEMO-OPT-003SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY

Progress evidence (sample layout)

Every progress file is dated and labeled with its source, so you always know whether we saw it ourselves, saw it on live video, or received it from the supplier. This sample contains no real photos: the boxes below are SAMPLE placeholders.

SAMPLE placeholder
P-05 · Racks of fired mugs
Live video screenshot by OSMANTH
2026-10-23 14:32
SAMPLE placeholder
P-06 · Kiln area
Live video screenshot by OSMANTH
2026-10-23 14:36
SAMPLE placeholder
P-07 · Glaze test tiles
Sent by supplier (WeChat)
2026-10-24 09:15
SAMPLE placeholder
P-04 · Forming line
Sent by supplier (WeChat)
2026-10-20 10:20
SAMPLE placeholder
P-02 · Cartons in stock
Sent by supplier (WeChat)
2026-10-06 16:05
SAMPLE placeholder
VC-01 · Video call record
10 min, OSMANTH and Mr. Chen
2026-10-23 14:30
RefSourceDate (UTC+8)What it supportsStatus
P-05, P-06Screenshots taken by OSMANTH during live video VC-0110-23 14:32–14:36M3: 50% formed & first firingObserved remotely
P-07Photo sent by supplier10-24 09:15R-02: sage green glaze rejectedSupplier Stated
P-01 – P-04Photos sent by supplier10-06 – 10-20M1, M2Supplier Stated

How we label progress evidence

If you need independent confirmation before a payment, an on-site check can be added and quoted separately.

Osmanth China Business Services · SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY — not a client case. All names, numbers and addresses are invented.Page 3 of 5
SAMPLE TEMPLATE
FOR DEMONSTRATION ONLY
OSMANTHOSM-DEMO-OPT-003SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY

Supplier Confirmation Form — excerpt (SCF-03)

The factory may voluntarily sign this form. A signature confirms only what the factory states. It is not independent verification.

CompanyDemo Yuxin Ceramics Co., Ltd. (fictional)
Order / productPO-DEMO-0427 · Stoneware mug 350 ml, 3 colors
Quantity12,000 pcs (cream 4,000 · navy 4,000 · sage green 4,000)
Progress statedForming complete for all 12,000 pcs; cream and navy glazed; sage green glaze being re-mixed
Delivery date stated8,000 pcs (cream, navy) ready 2026-11-20; 4,000 pcs (sage green) ready 2026-11-27
Authorized contactMr. Chen, production manager (stated)
Supplier signature & company seal
Demonstration — intentionally left blank
Date
2026-10-25 (demo)

Risk / delay log

RefOpenedIssueImpactNext stepStatus
R-0110-06Materials 1 day lateNone (recovered by 10-08)—Closed
R-0210-24Sage green glaze rejected in supplier’s color check+7 days for 4,000 pcsClient to decide: one shipment on 11-27, or split shipmentOpen
R-0310-25New sage green color not yet approved by clientPossible further delayRequest dated photo of new test tiles next to client’s color sampleOpen
Osmanth China Business Services · SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY — not a client case. All names, numbers and addresses are invented.Page 4 of 5
SAMPLE TEMPLATE
FOR DEMONSTRATION ONLY
OSMANTHOSM-DEMO-OPT-003SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY

Next steps (week of 10-26)

  1. Client decision on R-02 (single or split shipment) — requested by 10-28.
  2. Request dated photos of the new sage green test tiles beside the approved color sample (R-03).
  3. Weekly call with Mr. Chen on 10-30; request evidence for M4 (glazing).
  4. Optional: on-site check of packing before the balance payment — quoted separately.

Limitations of this report

Conclusion wording

Based on supplier statements and one remote video check, forming appears complete and two of three colors are on schedule. The sage green color is at risk of a 7-day delay (R-02). No item in this update was independently verified in person.
Prepared by
[Coordinator — demo]
Date: 2026-10-25
Reviewed by
[Reviewer — demo]
Date: 2026-10-26
About this sample. This is a sample template for demonstration only. The companies, people, order, dates and evidence are invented. It is not a client case.
Limitation of liability — due diligence, not a guarantee. This report reflects what we could observe or verify on the dates shown, using the documents and access available to us. It cannot rule out deliberate deception (such as falsified documents, staged sites or hired people) or changes after our checks, and it does not guarantee any supplier’s performance, quality, delivery or payment safety. Business and payment decisions remain the client’s. Our liability is limited to the fee paid for this service, and we are not liable for indirect or consequential losses. Full terms: osmanth.com/how-we-work#liability
Osmanth China Business Services · SAMPLE TEMPLATE — FOR DEMONSTRATION ONLY — not a client case. All names, numbers and addresses are invented.Page 5 of 5