A pre-shipment inspection (PSI) is a check of the goods before they leave the factory or the consolidator — usually when production is finished or nearly finished, and often when a portion of the order is already packed. For a US buyer on a first or small order, it is one of the last chances to catch a wrong count, a finish that does not match the approved sample, or a packing method that will not survive the voyage, while the goods are still in China and still in the seller's control.
This guide is a practical checklist for arranging that inspection on a small order: when to schedule it, what to put in the brief, what a useful report contains, and what to do with a fail or a “hold.” It is due diligence guidance, not a quality certification, not legal advice, and not a substitute for your contract. Inspection companies set their own prices; this site has no list prices, and this article does not quote competitors’ fees.
1. When a PSI actually helps — and when it is too late
A pre-shipment inspection is most useful when there is still time to rework, repack, or hold the goods before they are handed to the carrier. In practice, many inspectors ask to visit when production is complete or nearly complete, and when a large share of the order is packed or ready to pack, so they can count cartons and open a sample of finished units. If the goods are already on the water, this is no longer a pre-shipment check.
It is also late if you have never approved a sample. A PSI compares finished goods with a standard you already accepted — a signed golden sample, a written specification, photos with measurements, or a marked-up pre-production sample. If that standard does not exist, the inspector can still report what they saw, but “pass” and “fail” become arguments rather than measurements.
For small orders, a PSI is not automatic. It is worth doing when a defect would be expensive to fix after arrival, when this is a first order with a new supplier, or when the packing and labeling matter as much as the product. It is weaker as the only control on a supplier whose legal identity or production address you have not yet verified.
2. Build the calendar backwards — including the 2027 Spring Festival shutdown
Work backwards from the date you need the goods, then from the sailing or air-freight date, then from the inspection date, then from the date production must be finished enough to inspect. Leave time after the visit for a rework and a short re-check if the first report is a fail or a hold.
If the order will run toward early 2027, put the official holiday dates on the same calendar. The General Office of the State Council’s notice on the 2027 public holiday schedule (国办发明电〔2026〕10号, published 5 November 2026) lists the Spring Festival holiday as 5–13 February 2027, and National Day as 1–7 October 2027. Factories, inspectors and freight forwarders often slow down or close for some days on either side of those official holidays as well. Those shoulder days are not in the notice; confirm them in writing with the supplier and the inspector, and do not treat a promised “we will ship before the holiday” as a plan unless the inspection window still fits.
The official notice is here: www.gov.cn, 国办发明电〔2026〕10号.
3. What to put in the inspection brief
A useful visit starts with a written brief, not with “please check the quality.” Send the inspector, and keep a copy for yourself:
- The Chinese legal name and Unified Social Credit Code of the company whose premises you want visited, and the production address. These should match the entity you already checked on GSXT and, if you went earlier, the address in the small-order factory visit checklist.
- The purchase order or proforma: item names, quantities, colors, sizes, and any SKU or batch codes.
- The approved sample standard: photos, measurements, materials, and what “same as sample” means for this order. If a physical golden sample will be at the site, say so; if the inspector should bring or collect it, say that too.
- Packing and labeling rules: carton size and strength, inner packing, barcodes, shipping marks, and any destination-country marks you required in the order.
- What “enough” units to open and measure looks like for this order. Industry sampling plans (such as ISO 2859-1 / ANSI-ASQ Z1.4 style AQL tables) are widely used by inspection firms, but they are industry methods, not a Chinese or US government rule for your contract. If you want a particular plan or a particular number of cartons opened, write it down. If you do not, ask the inspector to state the method they will use, in the report.
- Access and timing: who meets the inspector, whether photos and a short video are allowed, and whether packed cartons may be opened and resealed.
- What happens if the result is a fail or a hold: who is notified first, whether shipment is to be stopped, and how a re-inspection would be requested.
If you cannot attend, the same logic as a hired factory visit applies: scope, access limits and the evidence pack must be written down before anyone travels. A PSI and a factory-capability visit are not the same job. One looks at finished goods and packing on a given day; the other asks whether that address is a factory, and whether it belongs to the company you contracted with.
4. What a useful report contains
Ask for a dated report that you can keep with the order file, not only a verbal “it’s fine.” A useful pack usually includes:
- The date, the address visited, and the name of the company on site — ideally matched to signage, a business license on the wall, and the legal name in your brief.
- How many units or cartons were present, how many were opened, and how those units were chosen.
- Measurements and photos against the approved sample: dimensions, color, finish, function tests you asked for, and any missing parts or mixed SKUs.
- Packing and labeling photos: carton marks, inner packing, palletizing if relevant, and whether packed quantities match the packing list.
- A clear result — pass, fail, or hold — tied to the criteria in your brief, plus a list of defects with counts, not only adjectives.
- The inspector’s limits: what they did not see, what they were not allowed to open, and whether production was still unfinished.
A clean report is evidence of what was seen that day. It does not guarantee the unopened cartons, the units produced after the visit, or the condition of the goods on arrival. It also does not prove that the company on the door is the company on your contract; that remains a GSXT and payment-name question.
5. If the report is a fail or a hold
Stop the shipment until you have a written plan. A typical sequence is:
- Send the report to the supplier on a channel you already trust, and ask for a written rework plan with a date.
- Decide, in writing, which defects must be reworked, which you will accept with a discount or a credit, and which are a reason not to ship.
- If rework is agreed, schedule a short re-inspection of the failed points rather than taking a promise in a chat message as the close of the issue.
- Do not pay a remaining balance, and do not agree to a “ship now, fix later” arrangement, until the evidence matches what you agreed.
If the supplier goes quiet after you share a fail report, treat that as a hold on payment and shipment. The steps in our guide on a supplier who goes silent after a deposit apply whenever money or goods are already at risk.
6. Who can do the inspection
You can hire a third-party inspection company, ask a trusted person on the ground, or — if you are already in China — go yourself with the same brief. The useful question is not the brand name on the inspector’s badge. It is whether the person at the address will follow your brief, open enough units, and give you dated evidence you can act on.
If you hire a firm, do a basic identity check on that firm as well: Chinese legal name, Unified Social Credit Code, and a GSXT record that matches the company on the contract and the invoice. An inspection report issued in an English trading name you cannot tie to a registered entity is harder to rely on later.
This is not legal, customs or tariff advice, and it is not an instruction to use a particular sampling standard or a particular firm.
7. How Osmanth can help
Osmanth China Business Services can help, where we accept the task, with on-site visits, production follow-up, and entity checks on the factory or the inspection company you name. Every request is assessed first. Availability depends on dates and location. There are no list prices on this site; every job is quoted individually.
This article is a checklist for arranging a pre-shipment inspection, not an offer to inspect a named factory, and not a guarantee of product quality or of on-time shipment. If you want help scoping a task, start at Contact. For the limits of what a report can and cannot prove, see how we work.
Sources
- General Office of the State Council of China, Notice on the 2027 public holiday schedule (国办发明电〔2026〕10号, published 2026-11-05; Spring Festival February 5–13, 2027; National Day October 1–7, 2027).
- National Enterprise Credit Information Publicity System (GSXT), gsxt.gov.cn, for matching the legal entity at the inspection address, and the inspection company if you hire one.
Checked 2026-11-23. Sampling plans mentioned above are industry methods, not a requirement of the official sources listed here. Holiday dates for later years are set by the State Council each year; check the current notice.
Limits of this guide
- We are not your lawyer, customs broker or quality-assurance certifier, and this is not legal, customs or tariff advice.
- A pre-shipment report records what was seen on the day. It does not guarantee the rest of the lot, later production, or the condition of the goods on arrival.
- What the supplier must accept, rework or compensate depends on your contract, not on this checklist.
FAQ
When should I schedule a pre-shipment inspection?
Usually when production is finished or nearly finished, and a large share of the order is packed or ready to pack, with enough time left to rework and re-check before the goods are handed to the carrier. Once the goods are on the water, it is no longer a pre-shipment check.
Is a factory visit the same as a pre-shipment inspection?
No. A factory visit asks whether the address is a factory and whether it belongs to the company you contracted with. A pre-shipment inspection looks at finished goods and packing against a standard you already approved.
Does a clean inspection report guarantee the whole order?
No. It is evidence of what was seen that day. It does not guarantee unopened cartons, later production, or the condition of the goods on arrival, and it does not prove that the company on the door is the company on your contract.
Do I have to use an official AQL sampling plan?
No. Plans in the ISO 2859-1 / ANSI-ASQ Z1.4 style are widely used by inspection firms, but they are industry methods, not a government rule for your contract. If you want a particular plan or a set number of cartons opened, write it in the brief and ask the inspector to state the method in the report.